The client wanted the system rated based on condition and capacity. The project was such an interesting study. Why did you select this project for the article? The public works director wanted our help in developing an easy-to-use plan that told them what needed to be replaced and at what level of urgency. It had been built piecemeal over the decades. The system ranged in age from 50-100 years. We interviewed John about the article, asking him about the project and his background with GIS and PCSWMM.Ĭan you tell us about the catalyst for the project?Ī 600-acre site was facing failing infrastructure. It discusses a Kansas municipality’s stormwater study, which analyzed a historic portion of town. ![]() Affinis project engineer, John Spell, PE recently wrote an article for APWA’s Reporter magazine.